After one week of scanning the platform Project in would contain seven Scan entries. Each Scan entry in the platform Project would be name AutoImport ExternalVA
Single scan task running multiple times per day (Single Scanner)
...
EXTERNAL SCANNER | SCAN NAME PREFIX | SCAN IDENTIFIER | MERGE MULTIPLE SCANS | MERGE MULTIPLE SCANNERS |
---|---|---|---|---|
MyExternalScanner | AutoImport | ExternalVA | TRUE | FALSE |
The two scans that run at 09:00 and again at 16:00 would be merged into a single Scan entry in the Project. If the scan runs every day at 09:00 and again at16:00 for seven days, after one week of scanning the platform Project would contain seven Scan entries. Each Scan entry in the platform Project would be name “AutoImport ExternalVA”
Multiple scan tasks running once per day (Single Scanner)
...
EXTERNAL SCANNER | SCAN NAME PREFIX | SCAN IDENTIFIER | MERGE MULTIPLE SCANS | MERGE MULTIPLE SCANNERS |
---|---|---|---|---|
MyExternalScanner | AutoImport | ExternalVA_UK | FALSE | FALSE |
MyExternalScanner | AutoImport | ExternalVA_US | FALSE | FALSE |
If the two scan tasks run on a daily basis for seven days, after one week of scanning the platform Project would contain 14 scan entries. Scan entries in the platform Project (for the daily UK scan tasks) would be named “AutoImport ExternalVA_UK” whilst Scan entries in the platform Project (for the daily US scan tasks) would be name “AutoImport ExternalVA_US”
Multiple scan tasks running multiple times per day (Single Scanner)
...
EXTERNAL SCANNER | SCAN NAME PREFIX | SCAN IDENTIFIER | MERGE MULTIPLE SCANS | MERGE MULTIPLE SCANNERS |
---|---|---|---|---|
MyExternalScanner | AutoImport | ExternalVA_UK | TRUE | FALSE |
MyExternalScanner | AutoImport | ExternalVA_US | TRUE | FALSE |
The platform will merge the daily 09:00 and 16:00 repetitive scans into their own Scan entry in the platform Project. If the two scans run every day at 09:00 and 16:00 for seven days, after one week of scanning the platform Project would contain fourteen Scan entries. The Scan entries in the platform Project (for the UK scan tasks), of which there would be seven in total, would each be named “AutoImport ExternalVA_UK”, whilst Scan entries in the platform Project (for the US scan tasks), of which there would also be seven in total, would each be named “AutoImport ExternalVA_US”
Scan task running once per day (Multiple Scanners)
...
EXTERNAL SCANNER | SCAN NAME PREFIX | SCAN IDENTIFIER | MERGE MULTIPLE SCANS | MERGE MULTIPLE SCANNERS |
---|---|---|---|---|
MyExternalScanner_London | AutoImport | ExternalVA | FALSE | TRUE |
MyExternalScanner_NewYork | AutoImport | ExternalVA | FALSE | TRUE |
The platform will merge the daily scan results from each external scanner into their own Scan entry in the platform Project. If the two scans run daily for seven days, after one week of scanning the platform Project would contain seven Scan entries. Each Scan entry in the platform Project would be name “Global Multi Import”
Scan task running multiple times per day (Multiple Scanners)
...
EXTERNAL SCANNER | SCAN NAME PREFIX | SCAN IDENTIFIER | MERGE MULTIPLE SCANS | MERGE MULTIPLE SCANNERS |
---|---|---|---|---|
MyExternalScanner_London | AutoImport | ExternalVA | TRUE | TRUE |
MyExternalScanner_NewYork | AutoImport | ExternalVA | TRUE | TRUE |
The platform will merge the daily 09:00 and 16:00 repetitive scan results from each external scanner into their own Scan entry in the platform Project. If the two scans run twice a day for seven days, after one week of scanning the platform Project would contain seven Scan entries. Each Scan entry in the platform Project would be name “Global Multi Import”